Repair and strehghtening of state road No 7 Zukowo - Chyzne, section Zukowo - Gdansk

Constructing the project

Scope of works:

  • rebuilding 7,2 km
  • excavations – 6.700 m3
  • embankments – 6.700 m3
  • stabilization – 2.650 m3
  • crushed stone aggregate stabilized mechanically – 8.600 t
  • bitumen mass – 32.200 t
  • concrete kerbs– 16.300 m
  • stone curbs – 1.400 m
  • concrete block pavement – 4.300 m2
  • boulder pavement – 1.700 m2
  • geocomposite on widened roadway – 18.000 m2
  • geocomposite on levelling – 9.000 m2
  • lightening
  • telecommunication engineering
  • landslide removal
  • water and sewerage supply networks
  • gas supply networks
  • traffic lights
  • culverts
  • bridge facilities (bridge and gangway)
Last updated: 8/16/2017