Constructing the project
Constructing the project
The contract included construction of two two-lane roadways with hard shoulders and a pavement adjusted to the pressure of 115 kN peraxle. The roadways are separated with a green strip, concrete stone pavement and steel safety barriers. Plastic antireflection protectors were installed on the barriers.
The scope of the contract also included execution of three bridges of the total length of more than 214 m. One of them constitutes a part of a road junction at the crossroads of state road No. 77 and Ogrodowa street. The two remaining objects are three-span viaducts over Polna streeet and the railway line of the direction Lublin - Stalowa Wola Rozwadów. Bridge works also included construction of culverts of the total length 171m.
Within the project we realized bus bays, bicycle paths and sidewalks as well as almost 10 km of access, local and distributor roads with exits to adjoining fields. We also executed rainwater and sewage drainage system and reconstructed gas, power and water supply networks.
The project in figures
- Bypass length: 3 km
- Local and access road length: 9,94 km
- Traffic lane width: 3,5 m
- Strengthened shoulder width: 2x2 m
- Ground shoulder length: 2x1,25 m
- Earth works: 381 588m3
- Subbases: 219243m2
- Pavements: 155 304m2
- Sidewalks: 9632m2
- Finishing works: 76 305 m2
- Rainwater system: 5,6 km
- Steel safety barriers: 5172 running meter
- Road signs: 228 pieces
- Road marking: 3823m2