c

Reconstruction of the Lotnicza Street In Wroclaw

Additional information

Cycle of viaduct construction shortened to 6 months with the exclusion of tram traffic. The schedule assumed to hand over both the tramline and road in the same time. Despite many obstacles we have encountered during work – collision with the network of underground utilities more than 200 missiles of World War II, both assumption were fulfilled. Within three weeks sapper team searched about 60 thousand square meters of land to ensure people’s safety.

 

Project In figures

  • Lenght of the north road: 2,4 km
  • Length of the south road: 2,6 km
  • Length of viaduct:70 m
  • Bicycle path: 6700 square meters
  • Length of tramline: 2,97 km
Last updated: 8/16/2017

Search or filter all our projects

Result

loading