Construction of carriageway of eastern provincial road Bielany-Lany- Dlugoleka

Project execution

Skanska commenced the work from Stawowa street in Siechnice and will finish at Odrzanska street in Łany. As part of this task, Skanska is required to build:

  • three bridge constructions over Oława and Odra rivers, with a lenght of 102, 120 and 286m
  • two flyovers over the areas with high flooding risk with a lenght of 614 and 532m
  • 14 meter long viaduct over Odrzanska street in Łany
  • 15 underpasses for animal crossing.

The project also includes an overhaul of an old and construction of a new technical infrastructure i.e. storm drainage facilities, sewage system, gas and water pipelines, telecommunication network and electrical services etc. Side walks for pedestrians and lanes for cyclists are going to be built along the road. We are also planning to install 1700 square meters of soundproof/acoustic screens and raise 851,000 cubic meters of embankments.

Last updated: 8/16/2017

Search or filter all our projects

All projects
  • All projects
  • Offices
  • Roads and bridges
  • Hydrotechnincs and ecology
  • Railways and trams
  • Cultural and monuments
  • Aviation
  • Life sciences
  • Industrial and logistics
  • Healthcare
  • Sports and recreation

Result

Sort by published date
  • Sort by published date
  • Sort by newest start date
  • Sort by newest completion date
  • Sort by oldest start date
  • Sort by name A-Z
  • Sort by name Z-A
loading