Grading of 66 hectares of area under construction of LG Philips LCD factory within the borders of "Euro-Park Wisłosan" Special Economic Zone in Tarnobrzeg - Sub-zone Wrocław - Kobierzyce in Biskupice Podgórne. The contract also included construction of internal roads and stormwater drainage system. We realized retention tanks, which enabled total elimination of local inundations. In the course of construction works carried out by Skanska more than 1 mln cubic meters of soil was excavated. 7,2 km of stormwater drainage system together with the remaining infrastructure was realized as well as 11,5 km of roads allowing heavy motor trucks traffic. Both road infrastructure as well as underground utilities build up integral part of LG Electronics industrial pole development. The fact that our Corean investor was satisfied with the works realized by our company was a great distinction for us.